Jubaili Bros Eng. Ltd. (Victoria Island Branch)
Project Details
This project carted to 90 endpoints.
Networking: Cabinet assembly and installation, network cabling and termination, network switch installation and configuration, wireless router configuration and installation, tower and blade servers provisioning and racking, dual WAN installation.
Other installations: Raised floors, cable trays (hidden undeath the raised floors), smoke detectors, air conditioning units, temperature/humidity/power sensor.
CCTV system: 4 Dahua 16-channel NVRs, 4 Dahua 24-port PoE switches, 50+ IP bullet cameras, and about 7 IP dome cameras.
However, it is worthy of note that all the points mentioned above were all installed by the in-house IT team except for installations listed under 'other installations' that were outsourced to external vendors.